Residual Solids and Lagoon Improvements
(Facilities replacement, upgrades and modernization)
Ensures the capability to transfer, dewater and store residual solids from water treatment plant processes for future reuse and disposal. Phase 1 of the work includes improvements to spent lime Lagoon A piping, embankments, inlet and outlet structures, and overflows as required by the Ohio Department of Natural Resources. Phase 2 work includes refurbishment of the plate and frame presses and sludge thickener tanks.
Status Phase 1: Completed
Status Phase 2: Under Construction
Estimated Completion: 2020
Project Cost, Phase 1: $1,950,000
Project Budget, Phase 2: $6,000,000
Heatherdowns Pumping Station Improvements
(Facilities replacement, upgrades and modernization)
Mechanical, electrical and structural improvements that will restore the reliability and efficiency of the pumping facility to maintain system pressures within the southwestern portions of the City. Work includes rehabilitation of pumps and check valves, electrical equipment replacements, HVAC upgrades and structural refurbishment.
Status Phase 1: Completed
Status Phase 2: Completed
Project Cost, Phase 1: $3,520,000
Project Cost, Phase 2: $2,900,000
West and East Plant Roof Replacement (Facilities Replacement, Upgrades and Modernization)
Provides a safe, secure environment for the protection of critical treatment processes and staff, as well as ensuring the long-term structural integrity of the existing buildings. Work includes removal and replacement of concrete roof panels and roofing materials; replacement of corroded steel support elements; and improvements to heating, ventilation and dehumidification and electrical systems.
Status:
Completed
Project Cost: $14,540,000
New Disinfection Facilities (Water Quality, Redundancy and New Buildings)
Replacement of existing facilities to significantly improve the capacity, reliability and safety of the chlorine disinfection systems. Work includes construction of new chlorine storage and feed building, feed equipment and solution piping, together with a new chlorine dioxide storage, generation, feed equipment and related feed piping.
Status:
Completed
Project Cost: $11,900,000